Following a tendering process, two parties enter into negotiations for a contract which they both confidently expect will materialise. One undertakes preparatory work or incurs expenses at the request of the other. But negotiations, through no fault of either party, break down, and a binding contract is never formed. The expenses, or remuneration for the work, clearly cannot be recovered as a matter of contract law. Must the party performing the work or incurring the expenses therefore bear the loss, or can the law of restitution be called in aid of recovery? This was the question which confronted Rattee J of the Chancery Division in the recent case of Regalian Properties plc & Another v London Docklands Development Corporation